Union of the Comoros: Validation of the AfDB Country Strategy Paper Completion Report (2021–2025)

Date: 10/08/2026

Type: Country strategy and program evaluation

Country(ies): Comoros

Status: Completed

Independent Development Evaluation (IDEV) validated the African Development Bank Group’s Country Strategy Paper (CSP) Completion Report (2021–2025) for the Union of the Comoros. The validation aimed to promote learning and accountability by independently assessing the achievement of results, the Bank’s performance, and the quality of the Completion Report, while drawing lessons to inform future country strategies.

The validation found that the CSP was relevant and strongly aligned with national and Bank priorities. Its focus on transport and energy infrastructure addressed major structural constraints, while the Bank demonstrated flexibility in responding to external shocks and mobilized substantially more resources than initially planned.

However, overall CSP performance was assessed as partially unsatisfactory. Despite progress in physical infrastructure and resource mobilization, only two outcomes out of five were achieved and five outputs were expected instead of six. Thirteen cross-cutting project outcomes were identified, of which six were fully realized. Implementation delays, procurement challenges, low disbursement rates, institutional capacity constraints, and weaknesses in the results framework limited effectiveness and efficiency. The sustainability of results also remains uncertain, particularly because of limited national capacity and infrastructure maintenance challenges.

The Completion Report was clear and well structured, with strong financial reporting. However, it provided limited evidence on outcomes and development impacts and insufficiently analyzed operational constraints and cross-cutting issues.

Key lessons:

  • Stronger Bank field presence and targeted technical assistance can accelerate implementation.
  • Quality upstream studies, advance procurement, and stronger project implementation capacities can reduce delays.
  • Stable project teams and robust monitoring and coordination systems are essential for sustainable results.
  • Analytical studies and knowledge products can strengthen policy dialogue and support reforms.